Public Meeting #1 Summary

Wescott Boulevard Improvements Project 

Public Meeting Summary

Overview

An in-person Public Information Meeting (PIM) was held for the Wescott Boulevard Improvements Project on October 9, 2025, from 5 -7 PM at Fort Dorchester Elementary School in North Charleston, South Carolina. In addition, a project-specific website was hosted on https://dorchestertransportation.com/all-projects-overview/wescott-boulevard, allowing individuals to review materials and provide input at their convenience, thereby expanding access for those unable to attend in person.

Upon arrival, attendees were asked to sign in and received a project handout outlining the project purpose, proposed improvements, anticipated schedule, and instructions for submitting comments. Dorchester County staff and their representatives were stationed throughout the meeting room. Five display boards were arranged in stations around the perimeter of the room, showcasing the project location, environmental and community resources, project development process and schedule, project overview, and existing and future traffic.

The public was invited to submit comments through the project website, by mail, or in person at the PIM. A total of 31 comments were received during the comment period, which ran from October 9, 2025, to November 9, 2025. Most comments received were focused on asking questions, identifying existing concerns, or offering suggestions for improvements.

Proposed Improvements

Dorchester County proposes roadway widening and improvements along Wescott Boulevard for approximately 1 mile from Ballantine Drive to Patriot Boulevard to reduce traffic congestion, improve safety, and enhance bicycle and pedestrian accommodation. The proposed project includes additional travel lanes, curb and gutter, drainage improvements, shared use path, sidewalk, and associated intersection improvements. The project also proposes a new roundabout at the intersection with Ballantine Drive.

Summary of Public Comments Received

This section provides a general overview of the public comments received during the public comment period from October 9 to November 9, 2025. Below are some common themes identified in the comments received:

Traffic Flow & Road Design

77% of commenters expressed concerns about how the proposed widening may affect daily travel, neighborhood access, and overall traffic operations.

  • Patriot Boulevard: Commenters emphasized that congestion at Patriot Boulevard should be addressed first, as they view it as the primary bottleneck in the corridor. Several commenters worried that widening Wescott Boulevard may simply shift congestion downstream rather than resolve it.
  • Left Turns: Many commenters shared that left-turn movements are already challenging and will become more challenging with four travel lanes. Difficulty exiting neighborhoods, particularly from Harroway Road, Ayscough Road, and Wildflower Way, was frequently mentioned.
  • Roundabout/Traffic Circle: A few commenters were opposed to the proposed roundabout at Ballantine Drive, citing confusion and potential for accidents. Some believe that existing traffic volumes do not warrant a roundabout and instead request alternative solutions such as a left-turn lane or a signalized intersection.
  • Raised/Landscaped Medians: Comments expressed concerns about restricted access for emergency vehicles and reduced ability for residents to make left turns.
  • Truck Restrictions: Residents also asked whether existing truck restrictions on both Wescott Boulevard and Patriot Boulevard would remain in place once the project is implemented.

Safety

Safety emerged as one of the most frequently cited themes, with 84% of comments focusing on designing for a variety of users, including pedestrians, cyclists, golf carts, and motorists.

  • Pedestrians & Cyclists: Residents expressed support for increased pedestrian and bicycle facilities. Additional safety measures were suggested, including:
    • Sidewalks on both sides of the roadway with guardrail
    • Greater separation between pedestrians, cyclists, and golf carts
    • Flashing pedestrian beacons, raised crosswalks, and improved visibility at intersections
    • Additional crosswalk locations for pedestrians and children walking to school, specifically at the intersection of Wescott Boulevard at Patriot Boulevard and Wescott Boulevard at Pebble Creek Boulevard.
  • Golf Carts: Commenters noted that golf carts frequently use the existing sidewalk and create conflicts with walkers and cyclists. Suggestions included clear rules, signage, enforcement, and designated golf cart paths.
  • Speed Management: Many residents raised concerns about existing speeding and fear speeding will increase with a wider roadway and want to ensure that the posted speed limit will not increase. Suggestions from commenters to minimize speeding along Wescott Boulevard include:
    • Increased speed limit enforcement (traffic cameras)
    • Radar feedback signs, speed cushions, or other traffic calming elements
  • Lighting & Visibility: Commenters emphasized the importance of improved visibility when turning onto Wescott Boulevard from subdivisions. Residents requested enhanced lighting at intersections and crosswalks, as well as clear, adequate lighting during construction to provide safety for drivers, pedestrians, and workers.
  • Emergency Access: Several commenters worried that raised medians may hinder emergency vehicles or slow response times.

Flooding & Drainage

16% of commenters noted recurring flooding along Wescott Boulevard, particularly near Harroway Road. Residents requested improved drainage infrastructure, ditch repairs, and plans for stormwater management associated with the widened roadway.

Environmental & Community Impact

61% of commenters raised concerns about environmental and community impact, and voiced interest in preserving the natural landscape, including trees and green space, and maintaining the quiet, residential character of the Wescott neighborhood. Maintaining trees and natural buffers, particularly around townhomes and near subdivisions. Some noted fear the expansion will turn Wescott into a busy thoroughfare like Dorchester Road or Ashley Phosphate Road.

Public Transit

10% of commenters asked whether CARTA services would be expanded to the Wescott area.

Future Development

10% of commenters expressed concern that the proposed improvements may lead towards a shift in commercial uses along the corridor.

Frequently Asked Questions

General

Improvements include constructing four 12-foot travel lanes with landscaped medians and dedicated turn lanes at intersections throughout the corridor. A roundabout is proposed at the intersection of Wescott Boulevard at Ballantine Drive. Other improvements include curb and gutter, drainage improvements, a 12-foot shared use path, and a 5-foot sidewalk.

  • Construction is anticipated to begin in early 2028 and take approximately 18 months to complete.
  • The community will be notified of major changes, or disruptions through general project communications, public notices, and/or posted signage. Construction phasing and traffic impacts will be shared in advance to help minimize disruption.
  • No off-site detours are anticipated during construction. Temporary lane closures may be utilized throughout the construction phase.

Traffic Flow & Road Design

  • Yes. The traffic analysis shows that without improvements, key intersections, including Wescott Boulevard at Ballantine Drive and Wescott Boulevard at Patriot Boulevard, are projected to exceed their capacity and operate in failing conditions by 2050. See table of Traffic Data here: https://dorchestertransportation.com/application/files/6117/5975/9996/4._Traffic_Data.pdf
  • The proposed improvements are designed to improve traffic flow and are expected to enhance operations at major intersections within the project area.

  • The decision to propose a roundabout or a traffic signal is based on traffic volume, safety, and long-term operational efficiency.
  • Roundabouts have been shown to substantially reduce serious injury crashes, improve intersection efficiency during peak hours, and accommodate continuous movement, especially in congested corridors.

  • A traffic study was performed along the corridor including traffic counts at Harroway Road, Ayscough Road and Wildflower Way to determine if these side roads would need a new traffic signal by the year 2050.  The placement of traffic signals is based on traffic volumes at each intersection, looking at both through movements and left turning movements.  Based on the traffic study performed, the percentage of left turning traffic onto Wescott Boulevard was not large enough to warrant a signal at these intersections.

  • Dorchester County is proposing improvements along Patriot Boulevard between Wescott Boulevard and Weber Boulevard as a separate project that is anticipated to begin construction Spring 2027. Design and construction of these two projects are being coordinated.  More information regarding Patriot Boulevard project updates and schedule can be found here: Patriot Boulevard: Dorchester County Transportation Sales Tax Program

Safety

  • The 12 foot off-street shared use path included in the project will provide separation from vehicle traffic and support safe two-way travel for pedestrians and cyclists.  In addition, it is proposed that landscaping will be provided between the roadway and shared use path to provide a visual buffer.

  • A shared use path is an off-street facility designed for both bicyclists and pedestrians, offering a physically separated space that supports two-way, non-motorized travel.
  • A dedicated bike lane is an on-street facility designed for bicycle use only. It typically runs in the same direction as vehicle traffic and is separated by paint or flexible posts.
    • Dedicated bike lanes are not included in this project.

  • Golf carts and other motorized vehicles are not permitted by law on shared use paths, which are designed exclusively for pedestrians, cyclists, and other non-motorized users.
  • Golf cart rules are typically handled through police enforcement

  • The proposed 30 mph speed limit on Wescott Boulevard will match existing conditions. 
  • Safety improvements include:
    • Dedicated turn lanes to reduce rear-end collisions.
    • Design includes curb and gutter which has been shown to slow traffic compared to the open shoulder condition that exists today.

  • The County will evaluate existing lighting and consider adding or upgrading roadway and crosswalk lighting where needed. Final lighting locations will be determined during detailed design.
  • The proposed design will remove obstructions to sight lines and provide clearer views when turning right or left from side streets.

  • The project team will coordinate closely with local emergency services throughout construction to ensure that emergency access is maintained at all times.
  • Construction phasing will be planned to minimize disruptions to response times and critical access routes.

Drainage & Flooding

  • Yes. The project team has reviewed existing drainage and will address stormwater conveyance within the right-of-way, including new grading to direct water to new and existing drainage infrastructure.
  • The proposed stormwater management improvements include using open channels and the addition of curb and gutter.

Environmental & Community

  • The County is committed to preserving grand trees and maintaining natural buffers wherever feasible; however, some trees and vegetation will need to be removed within the construction limits. Any trees removed as part of the roadway construction will be mitigated in accordance with City of North Charleston Tree Ordinances.

Public Transit 

  • At this time, CARTA has not proposed any new bus routes along Wescott Boulevard. Transit service decisions are made independently by CARTA based on ridership demand, system planning, and available funding.

Future Development

  • Dorchester County is not proposing any new residential developments as part of this roadway project. Any future private development would be subject to the City of North Charleston’s standard planning and zoning review processes, including required approvals, public notifications, and compliance with existing zoning regulations.

  • No zoning changes are included as part of the Wescott Boulevard Improvements Project. The roadway project is focused solely on transportation needs and does not modify land use designations or zoning classifications. Any future zoning proposals would go through the City of North Charleston’s separate public review process and would require approval by Planning Commission and City Council.