This project includes a new temporary traffic signal installation at the intersection of US Highway 17A and Village Ponds Drive. The intent is for the traffic signal to remain in place until such time that the Linger Longer Drive Extension project is completed and open to traffic.
The construction contract was awarded to J. Moore Electrical Contractors, Inc. The Notice to Proceed date was February 10, 2025 with a 30-day construction duration.
Construction Contract Value = $ 184,715.00